The maintenance carried out on a system to avoid failing is

  • A.breakdown
  • B.corrective
  • C.periodic
  • D.predictive
  • E.preventive
Objective

Question details

Exam body
BECE
Subject
Basic Technology
Year
2015 Paper 2
Question no.
#53
Type
Objective
Previous · Q52A revolving door is used to Next · Q54 The ability of a machine to perform its function satisfactorily is called

More from this paper

  • Q49The exclusion of rain from the building is the primary function of
  • Q50The type of door drawn below is
  • Q51Solid panel door is best used in the
  • Q55When a fault is detected in a system, the next step is to ______ the default.
  • Q56Which of these operations is NOT carried out in site preparation?
  • Q57All actions appropriate for retaining a machine to a given condition is normally…
See all Basic Technology 2015 Paper 2 questions
Teacha

Africa's learning & exam readiness platform. Built for students, tutors, and schools.

Platform

  • Courses
  • Mock Exams
  • Past Questions

For You

  • I'm a Tutor
  • I'm a School
  • Pricing

© 2025 Teacha. Built for African learners, tutors, and schools. Teacha is not affiliated with WAEC, NECO, or JAMB. All past questions are sourced from publicly available materials.

Privacy PolicyTerms of UseCookie Policy