A contractor agreeing to finish a work in 150 days employed 75 men each working 8 hours daily. After 90 days only 2/7 of the work was completed. Increasing the number of men by each working now for 10 hours daily, the work can be completed in time.

  • A.120 men
  • B.100 men
  • C.75 men
  • D.150 men