The time taken to do a piece of work is inversely proportional to the number of men employed. If it takes 30 men to do a piece of work in 6 days, how many men are required to do the work in 4 days?

  • A.20
  • B.35
  • C.45
  • D.60
  • E.
Objective

Question details

Exam body
JAMB
Subject
Mathematics
Year
2005
Question no.
#0
Type
Objective
Previous · Q0A polynomial in x whose zeros are -2, -1 and 3 is Next · Q0 The weight W kg of a metal bar varies jointly as its length L meters and the…

More from this paper

  • Q0Find the value of m if 13 m + 24 m = 41 m
  • Q0If 321 4 is divided by 23 4 and leaves a remainder r, what is the value of r?
  • Q0Simplify 3 1 / 2 - (2 1 / 3 * 1 1 / 4 ) + 3 / 5
  • Q0If the interest on N150.00 for 2 1 / 2 years is N4.50, find the interest on…
  • Q0Three boys shared some oranges. The first received 1 / 3 of the oranges and the…
  • Q0Evaluate \(\frac{(81^{\frac{3}{4}}-27^{\frac{1}{3}})}{3 \times 2^3}\)
See all Mathematics 2005 questions
Teacha

Africa's learning & exam readiness platform. Built for students, tutors, and schools.

Platform

  • Courses
  • Mock Exams
  • Past Questions

For You

  • I'm a Tutor
  • I'm a School
  • Pricing

© 2025 Teacha. Built for African learners, tutors, and schools. Teacha is not affiliated with WAEC, NECO, or JAMB. All past questions are sourced from publicly available materials.

Privacy PolicyTerms of UseCookie Policy