Question 7

The time taken to do a piece of work is inversely proportional to the number of men employed. If it takes 30 men to do a piece of work in 6 days, how many men are required to do the work in 4 days?

  • A.20
  • B.35
  • C.45
  • D.60
Objective

Question details

Exam body
UNIPORT
Subject
Mathematics
Year
2015/2016 Model 1
Question no.
#7
Type
Objective
Previous · Q6Water flows out of a pipe at a rate of 40πcm 3 per second into an empty… Next · Q8 If sin θ = ${-1/2}$ for 0 < θ θ 360°, the value of…

More from this paper

  • Q2A father decided to give 20% of his monthly income to his three children as…
  • Q3Divide 6x² - 13x + 5 by 2x - 1
  • Q4A polynomial in x whose zeros are 2, -1 and 3 is
  • Q5If x varies inversely as y and y varies directly as z, what is the relationship…
  • Q9If y = (1 - 2x)³, find the value of ${{dy}/{dx}}$ at x = -1
  • Q10Find the derivate of y = sin (2x³ + 3x - )
See all Mathematics 2015/2016 Model 1 questions
Teacha

Africa's learning & exam readiness platform. Built for students, tutors, and schools.

Platform

  • Courses
  • Mock Exams
  • Past Questions

For You

  • I'm a Tutor
  • I'm a School
  • Pricing

© 2025 Teacha. Built for African learners, tutors, and schools. Teacha is not affiliated with WAEC, NECO, or JAMB. All past questions are sourced from publicly available materials.

Privacy PolicyTerms of UseCookie Policy