Question 12

The time taken to do a piece of work is inversely proportional to the number of men employed. If it takes 45 men to do the piece of work in.5 days, how long will it take 25 men?

  • A.15 days
  • B.12 days
  • C.5 days
  • D.9 days
Objective

Question details

Exam body
UNIZIK
Subject
Mathematics
Year
2007/2008 Day 1
Question no.
#12
Type
Objective
Previous · Q11In a school 220 students offer biology or mathematics or both. 125 offer biology… Next · Q13 Simplify 52.40 - 5.7-3 - 45 -1.75 :

More from this paper

  • Q8Find the least length of a rod which can be cut into exactly equal strips each…
  • Q9A rectangular lawn has an area of 1815 square yards, if its length is 50 metre…
  • Q14A trader bought goats for N4,000.00 each. He sold them for N 180,000 at a loss…
  • Q15A 5.0g of salt was weighted by Amaka as 5.1g. What is the percentage error :
  • Q16Find correct to one decimal place 0.24633/0.306
  • Q17A basket contains green, black and blue balls in the ratio of 5:2:1, if there…
See all Mathematics 2007/2008 Day 1 questions
Teacha

Africa's learning & exam readiness platform. Built for students, tutors, and schools.

Platform

  • Courses
  • Mock Exams
  • Past Questions

For You

  • I'm a Tutor
  • I'm a School
  • Pricing

© 2025 Teacha. Built for African learners, tutors, and schools. Teacha is not affiliated with WAEC, NECO, or JAMB. All past questions are sourced from publicly available materials.

Privacy PolicyTerms of UseCookie Policy